项 目 介 绍
Project introduction
该工程为组合式膜结构形式,近似呈矩形,纵全长115.2米,跨间距7.68米,共15跨,前后悬挑18.5米。以钢柱和平面桁架为界,分为 15个独立膜单元,每个膜单元大体呈圆锥状,通过柱顶顶升结构给膜面施加预张力。
Beijing 101 Middle School Stand Stadium Membrane Structure
The project is a combined membrane structure. Its plan is an approximate rectangular of 115.2m long and 18.5m wide. There are 15 membrane units located upon 15 trusses with each span of 7.68m. Each membrane unit is similar to conoid. Membrane tension is fulfilled by pulling the suspending cables at the top of each membrane units.
竣工时间:2012年3月 Completion time: Mar. 2012
建设地点:北京 Construction site: Beijing
结构形式:张拉式和骨架式相结合 Structure form: Tension structure and framework structure
膜 面 积:2400平米 Membrane area: 2400 square meters
膜材型号:法拉利1002S PVDF膜材 Membrane material: Ferrari 1002S PVDF