该工程属于整体张拉式膜结构,平面形状为梯形,两端长度分别为9米和13米,纵向长度为42米。柱间距7米,共6跨,桁架悬挑长度不一,最长11米,最短7米,柱最高点12.3米,外拉两根稳定钢索。钢立柱提供支承吊点,膜单元通过调节两根吊索的长度施加预张力张拉而成形,每个膜单元的膜吊点高度不一,有序排列。

The Golf Training Course of Beijing Ming Tombs Membrane Structure
This project belongs to the tensile membrane structure. The plane shape is a trapezoid, the two ends are 9m and 13m wide respectively, and the length is 42m. Each column space of the six is 7m, the longest truss cantilever is 11m and the shortest 7m. The highest point is 12.3m. The steel column provides the support point to the pulling cable, and adjusting the pulling cable to tension the membrane. Each top point of the membrane unit is different, and they are carefully arranged. 

竣工时间:2007年5月                       Completion time:  May. 2007 
建设地点:北京                            Construction site:  Beijing
结构形式:张拉式                          Structure form:  Tension structure
膜 面 积:760平米                         Membrane area:  760 square meters
膜材型号:法拉利1002S PVDF膜材            Membrane material:  Ferrari 1002S PVDF